Albion House

Case Studies


Albion House

Downwell Demolition
£150,000
September 2015 - November 2015
Albion House
Scope of Work:
  • Removal of thermal insulation Residue from all of the concrete slabs of the 7 storey tower block. the floors of the building were sheeted off using polythene whilst operatives used scabbling machines to grind the residue from the concrete.
  • The waste was collected using H Type Vacs.
  • Several risers throughout the building contained asbestos insulating board (AIB) This was removed by creating air tight enclosures around the ducts and removing the board under controlled conditions.
  • All areas were cleared by an analyst before reoccupation certificates were issued for the areas.

 