Inner City Environmental given the role of the asbestos removal contractor for Eden Girls School project. Northeast Demolition appointed us to complete the works within a 10 week programme.

The asbestos removal was part of a phased redevelopment plan, with the old school building now needing to be demolished.

Scope of Work:
  • Prior to the start of the removal works the school building was decanted of students. They were relocated into the new school building which was constructed nearby.
  • Firstly the site had to have the hygiene facility established to provide suitable cleaning facilities for the workers.
  • Wearing the correct PPE the work area was pre-cleaned of non-ACM, ensuring that all objects and debris are removed. This helps to ensure that the work area and waste transit routes are free from debris.
  • 9 enclosures were erected using 1000-gauge polythene, incorporating the air locks and bag locks. CCTV systems installed in the enclosures to ensure that the works can be clearly viewed from the outside.
  • Smoke tests were completed in the enclosures to check that there are no gaps. Once this was completed, a 3-bar warning sign was displayed on the front flap of the air lock to designate the area as now live.
  • The removal works involved removing over 32m2 of asbestos insulation board (AIB) from the risers within the building. 20m2 of AIB was also removed from behind the external windows. There was also 20lm of pipe insulation and debris removed from other locations across the site.
  • All the asbestos waste was removed from the areas by firstly placing it into regulation waste bags, sealed with tape and then transported to the waste skip via the designated transit route.
  • Once the removal works were complete the areas were subjected to a fine clean using a H Type vacuum cleaner  and taking rags.
  • The area is then firstly inspected but the Supervisor before being handed over to an analyst who will conduct their own inspection, followed by an air-test being completed before handing the areas back to Northeast Demolition.
asbestos removal contractor for Eden Girls School
asbestos removal part of phased redevelopment plan
the asbestos waste was removed